Eastside Water Treatment Plant Expansion to 540 MGD – Part A, Headworks and Chemical Improvements; Contract No. 09-195
Plans & Specifications cost $275.00 for Full-Size Set or $5.00 for Plans & Spec on CD, Non-Refundable; Available Friday, June 5, 2009 at Dallas Water Utilities, 320 E. Jefferson Blvd., Rm. 215, Dallas, TX, 75203.
Pre-Bid Meeting: June 22, 2009 at 10:00 AM at Eastside Water Treatment Plant (Filter/Admin First Floor Training Room), 405 Long Creek Road, Sunnyvale, Texas 75182.
Project Manager: Mark Simon, P.E.; (214) 948-4324.
A PDF file version of Plans, Specifications and bid result tabulations can be obtained using Internet Explorer at the following City of Dallas ftp website: ftp://ftp.dallascityhall.com. Click on the folder for the appropriate contract number or Bid result Tabulations. Plan Holders list available at (214) 948-4584.
Bids Received on July 16, 2009 UNTIL 1:00PM. Bids Opened at 2:00PM on the same day. BID DATE EXTENDED TO JULY 16, 2009.
|