1) Agenda Item: SA for Design Modifications for Lake Fork Pump Station & Pipeline Inspection to Carter & Burgess - $2,847,217
•Authorize Supplemental Agreement No. 2  for professional services contract to provide design modifications and construction inspection for the Lake Fork Pump Station and 108-inch raw water transmission main •Services include construction inspection of Part 3 of the 108-inch Lake Fork raw water transmission main and construction inspection of the Lake Fork Pump Station
•Design modifications to the Lake Fork Pump Station's original design to permit efficient utilization and future expansion •Utilizing private inspection services was more efficient due to the extended distance from the metroplex